Company hired for TrumpâÂÂs reflecting pool makeover reportedly admits flaws in plan
Atlantic Industrial Coatings was given $14.7m no-bid contract and its findings contradict presidentâÂÂs claims of vandalism
The company hired to renovate the Lincoln Memorial reflecting pool has acknowledged that âÂÂhuman oversightâ and flaws in the repair plan caused the newly installed blue liner to peel and tear, according to documents reviewed by the New York Times that challenge Donald TrumpâÂÂs repeated claims of vandalism.
The president has repeatedly said vandals armed with knives or box cutters were responsible for tearing apart the poolâÂÂs âÂÂAmerican flag blueâ liner. But documents reviewed by the Times show that Atlantic Industrial Coatings, the company awarded the renovation contract, blamed its own execution of the repair work and a flawed design plan.
The justice department has charged several people with vandalizing the pool in early July, but prosecutors began moving to dismiss those cases on 31 July. A federal court filing said information later supplied by the interior department showed the damage was caused by a flawed installation and the rush to finish the project ahead of the countryâÂÂs 250th anniversary celebrations on 4 July, not vandalism.
The White House referred questions about the contractorâÂÂs report to the interior department. In a statement, a spokesperson for the interior department did not directly address the report, but blamed âÂÂmajor vandalismâ for the damage.
The spokesperson said Atlantic was âÂÂcontractually obligatedâ to remedy the repairs âÂÂand is well on its way to doing soâÂÂ.
Atlantic Industrial Coatings did not immediately return a request for comment.
Atlantic first acknowledged its mistakes in a 14 August report and provided additional details in early September, according to the documents. As a result of âÂÂhuman oversightâÂÂ, the company said crews failed to spray enough primer to properly bond the linerâÂÂs layers in certain places.
The company also said the design spelled out in the contract called for two chemicals to be used in separate layers of the liner even though the products ultimately proved incompatible. The chemical sprayed on top became hotter than the material below it could tolerate, causing the material underneath to blister and separate.
Atlantic said it had not anticipated that reaction because combining the two products in that manner was âÂÂvery uncommonâÂÂ.
Virginia-based Atlantic was awarded a $14.7m no-bid contract to repaint and waterproof the poolâÂÂs concrete floor in spring of this year. The approach had not previously been tested and was designed in part by the general manager of one of TrumpâÂÂs golf clubs, according to the Times.
The renovation was carried out on an accelerated schedule as the administration pushed to have the Reflecting Pool completed before the nationâÂÂs 250th birthday on 4 July.
Atlantic has said it would repair the pool again under the projectâÂÂs warranty.
Last month, Trump acknowledged the renovation had been rushed and that the contractor made mistakes, though he has not backed off his claims that vandals were responsible for much of the damage.
Writing on Truth Social, the president said the contractor had taken shortcuts while racing to complete the project for its 4 July opening. âÂÂAs with many jobs, there was also some contractor error done by rushing the job,â he wrote, claiming that the damage caused by those mistakes was limited to âÂÂa very small areaâ and was âÂÂrelatively inconsequentialâÂÂ.